title: "Applied Digital leases 150 MW to a hyperscaler for US$5.4bn over 18 years"
summary: "Applied Digital’s release and 8-K of 23 and 24 November: the lease’s terms, about US$2.0m per MW a year against June’s lease, how the build is financed, and the shares."
url: https://www.thetechbag.com/blog/applied-digital-5-4bn-lease-150-mw-hyperscaler
format: Note
desk: "Cloud & DevOps"
region: Global
published: 2026-11-26
published_at: 2026-11-26T19:54:00+05:30
facts_checked: 2026-11-26
author: TechBag (The TechBag Journal)
tags: ["Applied Digital lease","Applied Digital stock","APLD","Applied Digital hyperscaler","AI data centre lease","hyperscaler lease","Polaris Forge","Delta Forge","Macquarie Asset Management","critical IT load","CoreWeave","data centre financing"]
cover: https://www.thetechbag.com/blog/covers/applied-digital-5-4bn-lease-150-mw-hyperscaler.png
---

# Applied Digital leases 150 MW to a hyperscaler for US$5.4bn over 18 years

*Applied Digital’s release and 8-K of 23 and 24 November: the lease’s terms, about US$2.0m per MW a year against June’s lease, how the build is financed, and the shares.*

Note · Cloud & DevOps · By TechBag · Published 2026-11-26 · Facts checked 2026-11-26 · Canonical: https://www.thetechbag.com/blog/applied-digital-5-4bn-lease-150-mw-hyperscaler

The short version

1. Applied Digital leased 150 MW to an unnamed “tier-one investment-grade hyperscaler” on 23 November: about US$5.4bn over 18 years, or US$12.7bn over 33 with renewals.[1]
2. That is about US$2.0m per megawatt a year, against about US$1.65m in June’s 210 MW, 15-year lease. The company says the new lease carries “higher pricing”.[1][3]
3. Delivery is due to begin in the first half of calendar 2028. Watch the project financing Applied Digital plans for the build.[1]

Applied Digital, a Dallas company that builds and owns AI data-centre campuses and leases them to large cloud customers, has signed an 18-year lease for 150 MW of critical IT capacity with a “tier-one investment-grade hyperscaler” it does not name. The lease is worth about US$5.4bn over its base term, or about US$12.7bn if every renewal option is exercised over a 33-year total term, the company said on 23 November.[1] Delivery is expected to begin in the first half of calendar 2028, “subject to applicable development milestones, utility arrangements and regulatory approvals”. Neither the release nor the 8-K names the campus.[1][2]

## What a megawatt is worth

Spread evenly, US$5.4bn over 18 years is about US$300m a year, or about US$2.0m for each megawatt. In June Applied Digital signed a 210 MW, 15-year lease at its Delta Forge 2 campus in Alabama, worth about US$5.2bn over the base term: about US$1.65m per megawatt a year.[3] The new lease, the company says, “contains improved commercial terms over our prior leases, including higher pricing”.[1] The renewal years imply more again: the extra US$7.3bn over 15 renewal years averages about US$487m a year. The release does not give the rent schedule or any yearly increase.

**Figure: The new lease pays about 21% more per megawatt a year than June's Delta Forge 2 lease**

*Applied Digital: base-term contracted revenue per MW of critical IT capacity per year, US$ million, two leases signed in 2026*

New lease: 150 MW, 18 years (November)

US$2

Delta Forge 2: 210 MW, 15 years (June)

US$1.65

|  | Value (US$) |
| --- | --- |
| New lease: 150 MW, 18 years (November) | 2 |
| Delta Forge 2: 210 MW, 15 years (June) | 1.65 |

Source: Applied Digital, release of 23 November 2026 and fiscal Q1 2027 results release of 7 October 2026; TechBag arithmetic · as of 26 November 2026, 7:30pm IST · Base-term revenue divided by MW and by years in the base term; an average, not the rent in any one year

“Critical IT capacity” is the power delivered to the tenant’s servers. The grid connection must also carry cooling and the rest of the plant, which is why Applied Digital reports two numbers: more than 1.6 GW of contracted critical IT load and 2.2 GW of grid-connected peak load.[1]

## The portfolio, and how it is paid for

With this lease, Applied Digital says its contracted base-term lease revenue exceeds US$41bn, or about US$100bn with all renewals, and about 75% of the base-term figure comes from investment-grade customers.[1] At 31 August the figures were about 1.41 GW and US$36bn (US$86bn with renewals), across five campuses: Polaris Forge 1, 2 and 3 in North Dakota, Delta Forge 1 in Louisiana and Delta Forge 2. Polaris Forge 1 is leased to [CoreWeave](https://www.thetechbag.com/blog/coreweave-revenue-168-percent-interest-four-times-profit), Polaris Forge 2 to an investment-grade hyperscaler, and the other three to a tier-one investment-grade hyperscaler. It then had US$3.7bn of cash and US$6.4bn of debt.[3]

The chief financial officer, Saidal Mohmand, said the build will be financed with equity already funded from the balance sheet and through a US$5bn “programmatic equity partnership with Macquarie Asset Management”, then project debt backed by the lease.[1] The same morning the company closed a US$300m, 364-day bridge loan at SOFR plus 3 percentage points for Delta Forge 1; draws depend on conditions including state approval of electricity rates.[4] On 24 November it raised the commitment under its Series G preferred-stock agreement with B. Riley from US$2.0bn to US$2.5bn, leaving US$1.035bn to draw.[2]

## The shares, and what to watch

The release came out at 8:00am New York time on Monday 23 November, before the market opened. The shares closed that day at US$13.82, up 20.3% from US$11.49 on 20 November, fell 11.6% to US$12.22 on 24 November and closed at US$12.29 on 25 November, Nasdaq’s data show.[5][6] We assign no cause to either move. What to watch: the project financing for Delta Forge 1 and Polaris Forge 3, which Applied Digital expects to complete in January–March 2027, and for Delta Forge 2 in April–June 2027, and delivery on the new lease from 2028.[1] For another way a US cloud’s buildings are being financed, see [Blackstone’s BXDC deal with Amazon](https://www.thetechbag.com/blog/blackstone-bxdc-buys-aws-data-centres-5bn-leaseback).

How we did this

Figures as of 26 November 2026, 7:30pm IST

The lease terms, portfolio totals, financing plan and delivery timing are from the release filed as Exhibit 99.1; the bridge loan from Exhibit 99.2; the Series G change from the 8-K’s Item 1.01. Figures at 31 August and the Delta Forge 2 lease are from the fiscal first-quarter 2027 release; the time of the lease release is from Applied Digital’s investor site. Our arithmetic: US$5.4bn ÷ 18 = US$300m a year, ÷ 150 MW = US$2.0m; US$5.2bn ÷ 15 = about US$347m a year, ÷ 210 MW = about US$1.65m; 2.0 ÷ 1.65 = 1.21; (US$12.7bn − US$5.4bn) ÷ 15 = about US$487m. These are averages of rounded base-term revenue, not rents in any one year. Adding 150 MW to 1.41 GW gives 1.56 GW; the company says “over 1.6 GW” and does not reconcile the two. The release does not say whether the new tenant is the one leasing the Delta Forge and Polaris Forge 3 campuses. Share prices are Nasdaq’s historical data; the moves are our arithmetic on closes.

Spotted an error? [Write to us](https://www.thetechbag.com/blog/standards#corrections); corrections are published at the foot of the piece.

Sources

1. [Applied Digital: Applied Digital Secures New 150 MW, 18-Year Lease with Tier-One Investment-Grade Hyperscaler (8-K, Exhibit 99.1)](https://www.sec.gov/Archives/edgar/data/1144879/000149315226054002/ex99-1.htm) — 23 November 2026; filed 24 November 2026
2. [Applied Digital: Form 8-K (Items 1.01, 3.02, 7.01) and Exhibit 10.1, letter agreement with B. Riley](https://www.sec.gov/Archives/edgar/data/1144879/000149315226054002/form8-k.htm) — dated 24 November 2026
3. [Applied Digital: Applied Digital Reports Fiscal First Quarter 2027 Results](https://ir.applieddigital.com/news-events/press-releases/detail/163/applied-digital-reports-fiscal-first-quarter-2027-results) — 7 October 2026
4. [Applied Digital: Applied Digital Announces $300 Million Senior Secured Bridge Facility (8-K, Exhibit 99.2)](https://www.sec.gov/Archives/edgar/data/1144879/000149315226054002/ex99-2.htm) — 23 November 2026
5. [Applied Digital: investor relations, press releases (times of the 23 November releases)](https://ir.applieddigital.com/news-events/press-releases) — read 26 November 2026
6. [Nasdaq: Applied Digital Corporation (APLD), historical prices, exchange data](https://www.nasdaq.com/market-activity/stocks/apld/historical) — sessions of 20 to 25 November 2026

**Disclosure.** TechBag is a software reseller: it earns when companies buy through it, including from vendors named here. The analysis is TechBag’s own; no vendor paid for or saw this piece before publication. Facts are labelled reported, TechBag count or our view. [How the Journal works](https://www.thetechbag.com/blog/standards).

**Read this next:** [Blackstone’s BXDC buys 75% of 13 AWS data centres at US$5bn; Amazon will rent them back](https://www.thetechbag.com/blog/blackstone-bxdc-buys-aws-data-centres-5bn-leaseback) — Another data-centre deal read from its filings: BXDC buys 75% of 13 AWS data centres, 647 MW, at US$5bn, and Amazon rents them back.

Go deeper on TechBag

- [CoreWeave’s revenue rose 168%; its interest bill was four times its operating profit](https://www.thetechbag.com/blog/coreweave-revenue-168-percent-interest-four-times-profit) — the tenant of Applied Digital’s Polaris Forge 1 campus
- [Big Tech's quarterly capex hit US$202bn, more than its operations brought in](https://www.thetechbag.com/blog/big-tech-ai-capex-quarterly-line) — the hyperscalers’ spending behind leases like this one
- [Nebius drops ARR after a US$325m one-off; plans US$40–45bn of capex](https://www.thetechbag.com/blog/nebius-drops-arr-325m-one-off-capex-40-45bn) — another AI infrastructure company’s build-out, read from its filings