title: "Aurionpro wins ₹100 crore AI data-centre order; one customer passes ₹400 crore"
summary: "Aurionpro’s NSE filing of 25 November: what the AI-ready data-centre work covers, the customer’s orders this year, and the order against July–September revenue."
url: https://www.thetechbag.com/blog/aurionpro-100-crore-ai-data-centre-order
format: Note
desk: "Cloud & DevOps"
region: India
published: 2026-11-25
published_at: 2026-11-25T19:21:00+05:30
facts_checked: 2026-11-25
author: TechBag (The TechBag Journal)
tags: ["Aurionpro order win","Aurionpro share price news","Aurionpro data centre order","Aurionpro news","Aurionpro","Aurionpro Solutions","DC Development Hyderabad","AI-ready data centre","hyperscaler India","MEP works","data centre construction India","Aurionpro results","liquid cooling"]
cover: https://www.thetechbag.com/blog/covers/aurionpro-100-crore-ai-data-centre-order.png
---

# Aurionpro wins ₹100 crore AI data-centre order; one customer passes ₹400 crore

*Aurionpro’s NSE filing of 25 November: what the AI-ready data-centre work covers, the customer’s orders this year, and the order against July–September revenue.*

Note · Cloud & DevOps · By TechBag · Published 2026-11-25 · Facts checked 2026-11-25 · Canonical: https://www.thetechbag.com/blog/aurionpro-100-crore-ai-data-centre-order

The short version

1. Aurionpro has an order of about ₹100 crore from DC Development Hyderabad Ltd to build an AI-ready data centre in southern India within nine months.[1]
2. The work is design, engineering and the mechanical, electrical and plumbing systems; it takes this customer’s orders past ₹400 crore.[1] [2]
3. The order equals 24% of Aurionpro’s ₹414.98 crore revenue for July–September. The shares closed at ₹562.45 on Wednesday.[4] [6]

Aurionpro Solutions has received “an additional order of approximately ₹100 crore” from DC Development Hyderabad Ltd for the “Development of an AI-ready data centre in Southern India”, to be carried out “Over the period of 9 months”. The order “expands the existing engagement with the customer and takes the aggregate value of orders received from the customer to in excess of ₹400 crore”. That is the company’s structured disclosure to the National Stock Exchange, filed at 16:54 on Wednesday 25 November; it dates the event to 19 November at 11:00.[1] Aurionpro announced the order that day on its own website, describing the customer as “a global hyperscaler”.[2]

## What Aurionpro is building

The filing describes the work as “comprehensive design, detailed engineering, and end-to-end execution of MEP works, for the first AI-ready data centre”. MEP is mechanical, electrical and plumbing: the power distribution, cooling and pipework that let a building hold and run servers. Aurionpro’s annual report says operators in India are adapting to AI with “AI readiness, higher rack density, and support for liquid cooling”, and that its own data-centre unit works in consulting, design, engineering, construction, certification and operations, including direct liquid and immersion cooling.[1] [5]

The buyer is a customer Aurionpro already serves. On 5 October it announced a ₹150 crore order from “a leading global hyperscaler” to supply, install, test and commission an AI-ready data centre in Navi Mumbai, also over nine months: the “third significant project” from that hyperscaler in less than a year, taking the projects to “close to ₹ 300 crores”.[3] The ₹100 crore order lifts the total past ₹400 crore. The filing gives DC Development Hyderabad’s company number, which shows an unlisted public company registered in Gujarat in 2020, and answers “false” to whether it belongs to the group companies of any Indian listed entity. It does not name an owner, and neither do Aurionpro’s releases.[1]

## How big the order is for Aurionpro

Data centres sit beside transit and smart mobility, banking, payments and AI in the businesses Aurionpro’s annual report lists.[5] The company reported revenue from operations of ₹414.98 crore for July–September, up 16.0% on a year earlier, and a profit of ₹50.20 crore. Its results split revenue into two lines. “Sale of Equipment and Product” more than doubled from the quarter before, to ₹188.77 crore, while “Sale of Software Services” fell to ₹226.21 crore; the cost of material, software and services rose from ₹107.23 crore to ₹199.22 crore. The results do not say which line the data-centre orders fall in.[4]

**Figure: Aurionpro’s equipment and product sales more than doubled in a quarter, to ₹188.77 crore**

*Aurionpro consolidated revenue from operations by segment, quarter, ₹ crore*

|  | Sale of Software Services | Sale of Equipment and Product |
| --- | --- | --- |
| Jul–Sep 2025 | 207.04 | 150.63 |
| Apr–Jun 2026 | 272.71 | 85.36 |
| Jul–Sep 2026 | 226.21 | 188.77 |

Source: Aurionpro Solutions, unaudited consolidated results · as of 30 September 2026

Against the ₹1,411.09 crore Aurionpro earned in the year to March 2026, the new order is 7.1% and the customer’s ₹400 crore-plus is 28%. The annual report warns that such projects “may sometimes require investment ahead of revenue and do not always progress evenly”.[4] [5] The shares closed at ₹562.45 on Wednesday, up 1.3% on Monday, before the filing.[6] The order runs to about August 2027; the next read on it is Aurionpro’s results for October–December.

How we did this

Figures as of 25 November 2026, 7:00pm IST

The order’s terms are quoted from Aurionpro’s Regulation 30 XBRL filing with NSE, which states the amount as “approximately ₹100 crore” in words (its numeric field reads 100). The filing’s field for the date the order was received reads 10 March 2026, while its date of the event is 19 November 2026 and Aurionpro’s release is dated 19 November; we use 19 November. We could not read Aurionpro’s earlier order filings on NSE or BSE, so the earlier orders are from its own releases; the release of 5 October does not name the Navi Mumbai buyer, and the two first projects are not itemised in what we read. The company number is read by its standard format (U for unlisted, GJ for Gujarat, 2020, PLC for public limited company); we did not find the company’s owner in a primary record. Our arithmetic: the order and ₹400 crore over revenue, the end of the nine months, the segment changes and the share-price change. Aurionpro reports in ₹ lakh; we convert to crore. Closes are from NSE’s daily price files.

Spotted an error? [Write to us](https://www.thetechbag.com/blog/standards#corrections); corrections are published at the foot of the piece.

Sources

1. [Aurionpro Solutions, disclosure under Regulation 30 (Para B): bagging/receiving of orders/contracts, XBRL filing (NSE)](https://nsearchives.nseindia.com/corporate/xbrl/REG30_PARA_B_2329_WebXMLFile_20261125_165430780.xml) — 25 November 2026
2. [Aurionpro, press release: “Aurionpro secures additional order of nearly ₹100 crore from global hyperscaler, expands AI-ready data center engagement in Southern India”](https://www.aurionpro.com/news/aurionpro-secures-additional-order-of-nearly-rs-100-crore-from-global-hyperscaler-expands-ai-ready-data-center-engagement-in-southern-india/) — 19 November 2026
3. [Aurionpro, press release: “Aurionpro Strengthens Data Centre Growth Momentum with ₹150 Crore Follow-on Order from Global Hyperscaler”](https://www.aurionpro.com/news/aurionpro-strengthens-data-centre-growth-momentum-with-inr-150-crore-follow-on-order-from-global-hyperscaler/) — 5 October 2026
4. [Aurionpro Solutions, outcome of board meeting: unaudited results for the quarter and half year ended 30 September 2026](https://www.aurionpro.com/wp-content/uploads/2026/11/AURIONPRO_31102026200551_ASL_Outcome_of_the_Board_Meeting_31102026Final_sd.pdf) — 31 October 2026
5. [Aurionpro Solutions, Annual Report 2025-26](https://www.aurionpro.com/wp-content/uploads/2026/09/Aurionpro-Annual-Report-2025-26.pdf) — September 2026
6. [National Stock Exchange of India, daily price files for the cash market, 23 and 25 November 2026 (AURIONPRO, series EQ)](https://nsearchives.nseindia.com/content/cm/BhavCopy_NSE_CM_0_0_0_20261125_F_0000.csv.zip) — 25 November 2026

**Disclosure.** TechBag is a software reseller: it earns when companies buy through it, including from vendors named here. The analysis is TechBag’s own; no vendor paid for or saw this piece before publication. Facts are labelled reported, TechBag count or our view. [How the Journal works](https://www.thetechbag.com/blog/standards).

**Read this next:** [India runs 1.8 GW of data centres; AI alone may add 26.3 GW of grid load by FY32](https://www.thetechbag.com/blog/india-ai-data-centres-power-gigawatts) — Where the build-out stands: India runs 1.8 GW of data centres, and AI alone may add 26.3 GW of grid load by FY32.

Go deeper on TechBag

- [India's large data centres run 90% full; Crisil sees a fivefold build to 7.5 GW](https://www.thetechbag.com/blog/india-data-centres-90-percent-full-crisil) — how full India’s data centres are, and how much more is planned
- [Black Box’s order backlog passed US$1bn, up 88%, on hyperscaler data centres](https://www.thetechbag.com/blog/black-box-order-book-1bn-hyperscalers) — another integrator’s order book from hyperscaler builds
- [RailTel wins ₹27.03 crore order for Andhra Pradesh’s Legal AI Assistant on Google Cloud](https://www.thetechbag.com/blog/railtel-27-crore-andhra-legal-ai-google-cloud) — another Indian order read from its exchange filing