The health minister’s statement of 16 November and NHS England’s contract notes: a two-year extension, 170 trusts signed up, and an 18-month re-tender starting in 2027.
The NHS in England will keep Palantir’s Federated Data Platform until March 2029 and then replace the contract through a new tender. NHS England has extended the contract, signed in November 2023 with up to £330m of spending forecast over seven years, by two years beyond its first term, which was due to end in March 2027.23 The health minister James Frith announced it in the House of Commons on 16 November: “the current contract will remain for two years, before coming to an end.”1
170
NHS trusts signed up to the platform
Hansard
142
trusts live, which the minister said means they have activated it
Hansard
137
trusts the minister said are “realising benefits”
Hansard
£330m
forecast spending over seven years; not a committed amount
NHS England
The platform runs on Foundry, Palantir’s data analytics product, and gives each hospital trust and integrated care board its own instance for operational data such as beds, waiting lists and staff rosters.23 The contract went to a group led by Palantir Technologies UK, with Accenture, PwC, NECS and Carnall Farrar, after a tender that drew seven bids.35 NHS England expected at least £25.6m of spending in the first year.3 The award notice gives a value of £182,242,760 and says the authority pays as services are consumed, so the value “could increase to a forecasted amount of £330m. This figure is also not a committed amount.”4
The term is built in steps: three years, then options of 24, 12 and 12 months, for seven at most.5 The contract formally began in March 2024. NHS England says the extension takes the end date to March 2029 and that “there are then 2 further 1-year extension options”.2 Asked whether Palantir’s involvement would end for good in 2029, the minister said: “I can confirm that the contract will end in March 2029.” Funding will continue “at the current annual rate”, a figure he did not give.1
The first term ends in March 2027; the extension runs to March 2029
NHS Federated Data Platform contract, award to planned end, November 2023 to March 2029
| Date | Event | Detail |
|---|---|---|
| Nov 2023 | Contract awarded | To a Palantir-led group; up to £330m over seven years |
| Mar 2024 | Contract begins | Initial three-year term |
| Nov 2026 | Extension announced | Two years, in the Commons |
| Jan 2027 | Market engagement | With patients, partners and suppliers |
| Mar 2027 | First term would end | Contracts Finder lists 15 February 2027 |
| Mar 2029 | Contract ends | Transition to the next platform |
Source: Hansard (16 November 2026); NHS England contract explainer; Contracts Finder · as of 17 November 2026 · Formal procurement begins in the second half of 2027; no date set
Market engagement starts in January 2027, formal procurement in the second half of 2027, and NHS England expects the whole process to take about 18 months; any eligible supplier will be able to bid.2 Maternity care will be the first area where other providers are asked to build new capabilities.1
This decision is a bridge, not the destination.
Members pressed on the figures and on the exit. Seamus Logan (SNP) said 29 trusts counted as live had said they were not, and put the number at 108; the minister replied with 170 signed up, 142 live and 137 realising benefits. Dame Chi Onwurah, who chairs the Science, Innovation and Technology Committee, said “if a break clause cannot be exercised because of continuity of care, it is not a break clause; it is a lock-in.” The minister said the contracts include exit and transition provisions, that migration is “possible in principle”, and later: “I can confirm today that we are not locked in.”1 NHS England says the NHS owns the intellectual property it commissions, including the platform’s data model, while Palantir keeps it in Foundry, and that all data stays in UK data centres.2
What to watch: the procurement terms, which the minister said will be issued “in the coming weeks”, and whether the two one-year options stay unused. The minister linked the new approach to the Microsoft outage of 12 and 13 November, whose cause we read here.1