Fibre spot prices are four to six times last year's as AI data centres take the supply

TrendForce's average spot prices for three optical fibres, 2025 against its 2026 estimate, and the supply behind them, as of 19 October

Illustration: The TechBag Journal

The glass that carries the internet has become one of the inputs AI data centres compete for. On 19 October TrendForce, the Taiwanese market-research firm, published average spot prices for three kinds of optical fibre and estimated a global shortfall of 180 million fibre-kilometres for 2026, out of demand of 577 million.1 Spot prices are what buyers pay outside long-term contracts. They are the first place a shortage shows, and the place a cabling contractor or a regional carrier buying in small lots meets it.

01The line: three fibres, one year

The steepest rise is in G.657.A2, the ITU’s bending-loss insensitive fibre, which TrendForce says is used for cabling inside data centres.17 G.652.D, the ITU’s standard single-mode fibre and what TrendForce calls mainstream telecom fibre, rose next. G.654.E, the cut-off shifted fibre TrendForce calls AI backbone fibre, used between data centres and in high-capacity backbones, rose least, from the highest starting price.12

Data-centre fibre went from 33 to an estimated 200 yuan a kilometre, the steepest of the three

Average spot price, yuan (CNY) per fibre-kilometre, 2025 against TrendForce's 2026 estimate

  • 2025 average
  • 2026 estimate
G.657.A2, in data centres200 yuan+506%G.652.D, telecom standard85 yuan+372%G.654.E, AI backbone170 yuan+278%
Table view
2025 average2026 estimateChange
G.657.A2, in data centres33200506%
G.652.D, telecom standard1885372%
G.654.E, AI backbone45170278%

Source: TrendForce, Average Spot Prices of Major Optical Fiber Products, 2025–2026 (chart in the 19 October 2026 release) · as of 19 October 2026 · 2026 is an estimate of the full-year average, published in October. Prices for finished fibre, not cable; multimode fibre is not covered

02What drives it

Demand. TrendForce names AI data centres, links between data centres and high-capacity backbones. Data centres take 18–20% of 2026 demand and, it projects, 30–35% in 2027; chipmakers and telecom operators are building related networks too. It says supply has been tight since late 2025.1 Corning’s numbers point the same way. Corning’s Optical Communications sales rose 32% to US$2.07bn in the quarter to June, with Enterprise Networks up 65% and, in Corning’s words, “Gen AI product sales growing significantly faster”. The same release recorded a multiyear supply agreement with Amazon for its US data centres.5

Supply. Fibre plants ran at 92% of capacity in 2026, and makers’ stock fell from four months in 2024 to one. New capacity starts with the preform, the glass rod fibre is drawn from, and adding preform capacity takes 18–24 months, so plans made now arrive late.1 In May, Corning and NVIDIA announced that Corning would expand its US fibre production capacity by more than 50%.6

Who says it is different this time. TrendForce argues this shortage differs from past telecom cycles because it comes from sustained new demand from AI data centres, not a one-off build.1 Corning’s Mike O’Day, announcing the Verizon deal, said “Gen AI and broadband expansion are part of the same transformative opportunity”.4 Both are sellers’ or forecasters’ readings. We found no published forecast of an earlier end to the shortage, and none of a later one.

Stock fell from four months to one, and the shortage is forecast to run until at least 2028

Fibre supply events and TrendForce's projections, 2024 to 2028

2024Four months of stock
2025Late 2025: supply tightens
20266 May: NVIDIA and Corning
20268 Sept: Verizon and Corning
202619 Oct: one month of stock
2027Q1 2027 already booked
2027Data centres 30–35% of demand
2028Shortage until at least 2028
Table view
DateEventDetail
2024Four months of stockfibre makers' inventory, per TrendForce
2025Late 2025: supply tightensAI data-centre demand, per TrendForce
20266 May: NVIDIA and CorningCorning to add over 50% to US fibre capacity
20268 Sept: Verizon and Corningabout 129M fibre-km, delivered 2027 to 2032
202619 Oct: one month of stock92% utilisation; 180M fibre-km short in 2026
2027Q1 2027 already bookedat some leading makers
2027Data centres 30–35% of demandTrendForce projection
2028Shortage until at least 2028TrendForce projection

Source: TrendForce (19 October 2026); Corning releases (6 May and 8 September 2026) · as of 19 October 2026 · Points placed within the year where the source gives only a year or a quarter

03What it means for a buyer

Carriers are buying years ahead. TrendForce says operators are moving from short-term purchases to long-term agreements.1 Verizon’s, announced on 8 September, covers “80+ million miles” of fibre and connectivity from 2027 to 2032, for its broadband build and for long-haul links between AI data centres.4 The leased lines, internet links and dark fibre that branches and campuses rent run over carrier networks like this one.

Lead times, not only prices. With some makers booked into the first quarter of 2027 and new preform capacity 18 to 24 months away, a project that needs new fibre runs in 2027 is competing for supply already promised.1 A campus or branch project buys installed cable, not bare fibre. We found no published figure for how much of a cabling quote the fibre is, so we cannot say how much of a four- to six-fold fibre price reaches a project budget. TrendForce does not price multimode fibre, which many in-building links use.2

What to watch. Corning’s third-quarter results are the next primary number: in July it guided core sales up about 16% to US$4.9–5bn.5 After that, whether the makers TrendForce describes as booked into the first quarter of 2027 extend that horizon, and whether more operators follow Verizon into multi-year contracts.1

Sources

  1. TrendForce, Optical Fiber Spot Prices Surge Severalfold in 2026, with Data Center-Driven Supply Shortages Expected to Persist Through 2028 — 19 October 2026
  2. TrendForce, chart: Average Spot Prices of Major Optical Fiber Products, 2025–2026 (unit: CNY/fkm) — 19 October 2026 Published in source 1.
  3. TrendForce (Chinese release): 2026年光纤现货报价倍数攀升,数据中心需求短缺或延续至2028年 — 19 October 2026
  4. Corning, Verizon and Corning announce multi-year, multi-billion dollar supply agreement for broadband expansion and next-gen AI infrastructure — 8 September 2026
  5. Corning, second-quarter 2026 financial results — 28 July 2026
  6. Corning, NVIDIA and Corning announce long-term partnership to strengthen US manufacturing for AI infrastructure — 6 May 2026
  7. ITU-T Recommendations G.652, G.654 and G.657: single-mode, cut-off shifted and bending-loss insensitive optical fibre and cable — approved August 2024
  8. Business Today: AI-led data centre boom is boosting fibre optic cable demand, says HFCL MD Mahendra Nahata — 23 July 2026